Eastside Interceptor Sewer Improvement Project -- Completed March 2003!
The King County Wastewater Treatment Division
has completed a sewer improvement project in downtown Renton to restore
lost capacity to the pipeline that carries water from Eastside
communities to the South Treatment Plant in Renton. Lost capacity was the
result of repairs following the 1965 earthquake.
King County worked closely with the City of Renton and residents in the
immediate construction area to reduce the negative impacts of noise,
vibrations, truck traffic and street closures during the 12-month
construction project. The project mostly affected sections of Houser Way South and Morris Avenue South.
Map of Construction Area, February
2002-March 2003
News Release, Feb. 6, 2002:
King County starts downtown Renton sewer improvement project
Construction Timeline
February-May 2002: Prepared and excavated access pits.
June-September 2002: Tunneled new sewer pipeline between
access pits.
October-December 2002: Installed new city water and
stormwater pipes.
February-March 2003: Repaved neighborhood streets and
completed project.
|